The Sheboygan Area School District's $121 million referendum to rebuild and remodel Farnsworth and Urban Middle Schools, held on November 5, 2024, received 65% voter support, and we are incredibly grateful for your support!
Work is well underway for the rebuilding and remodeling of both middle schools on their existing site. Take a look at the monthly Project Reports below to see the progress!
Farnsworth Preview
MONTHLY PROJECT PROGRESS REPORTS
- October 2025
- September 2025 - NEW Preliminary Renderings of Interior Spaces!
- August 2025
- July 2025
- June 2025
- May 2025 - First Look at Exterior Renderings!
- April 2025
- March 2025
- February 2025
- January 2025
October 2025
September 2025 - NEW Preliminary Renderings of Interior Spaces!
August 2025
July 2025
June 2025
May 2025 - First Look at Exterior Renderings!
April 2025
March 2025
February 2025
January 2025
On November 5, 2024, the Sheboygan Area School District asked the community to invest $121 million to rebuild and remodel Urban and Farnsworth Middle Schools at the current sites. Both schools are approaching 100 years old, and have similar, significant challenges.

Aging Infrastructure
- Roofs are at or near the end of their service life.
- Windows and doors need replacement.
- Exterior masonry needs repair.
- Spaces are not compliant with the ADA.
- The plumbing systems are in poor condition.
- The heating/ventilation (HVAC) systems are inefficient and at the end of their service life.
- Lack of air conditioning.

Safety & Security
- Fire alarms and sprinkler systems do not meet current codes.
- Parking lots and sidewalks are in poor condition.
- Main entrances are secure, but do not meet current standards.
- Bus and parent drop-off/pick-up is poorly configured, creating safety concerns.

Inadequate Classrooms & Support Areas
- Most classrooms are too small.
- There is limited space for hands-on learning and student collaboration.